raazshah661 raazshah661
  • 03-09-2020
  • Mathematics
contestada

A can do a piece of work in 20 days and B can do it in 12 days,B work for 9 days,in how many days A alone can do the work​

Respuesta :

roseheart889 roseheart889
  • 03-09-2020

Answer: 9

Step-by-step explanation:

Answer Link

Otras preguntas

What is a logical conclusion based on observed evidence
A byproduct of Oklahoma’s oil production, __________ is used in disinfectants and pharmaceuticals.
What type of chemical reaction is used by liver cells when synthesizing glycogen from glucose
round 0.505 to the nearest hundredth
When you are winning at poker and explain to others at the table that you are good at cards and tend to have good luck, what type of attribution error are you m
In the xy-plane, if line k has negative slope and passes through the point (−5,r), is the x-intercept of line k positive?
HELP PLEASE!!!!! HELP What is the number in scientific notation? Drag the answer into the box to match the number. 855,000,000,000 A: 8.055 x 10 ^-8 B: 8.5 x
Which values are solutions to the inequality –3x – 4 < 2? Check all of the boxes that apply. -4 -2 0 3
43-44 please and thanks
simplify expression using mental math 2+[-3]+(-3)