Six workers can plaster the exterior of a building in 5 hours. If the job is to be completed in only 3 hours 45 minutes, how many workers will be needed?​

Respuesta :

ecamarda ecamarda
  • 03-11-2020

Answer:

Step-by-step explanation:

each worker works 50 min so if you only need 225 min thrn you will need 4.5 workers

Answer Link

Otras preguntas

What caused chan-bo to get into trouble with the ministry for the protection of state security?
mexican flag What does each color represent ? 3. When was the flag adopted and what is the story behind the eagle and the serpent? 4. Were there earlier
Solve kx + 8 = 4 for x.
How many strands of dna are used to make complementary strands of dna?
The word which means to cut into two parts is _____. dichotomy morphology nomenclature
Kathy is 6 years younger the Bill. Twelve years ago, Bill was twice as old as kathy was then. How old are they now?
What do you call an egg that's turnt up
Number 16 plz I need help
How many lawns go in to 15 and 92
I need help with #13. If you help me and write everything it's asking I will mark you as the brainiest. Thank you