5 men take 45hours to build a wall.how long will it take 9men working at the same wall?​

Respuesta :

Аноним Аноним
  • 04-03-2022

Answer:

25 hours

Step-by-step explanation:

It takes 5 men 45 hours to build a wall.

So, if no. of men increases by 1.8 [∴ 5 x 1.8 = 9],

then time taken reduces by that same amount.

=> 45 hours / 1.8

=> 45 / (9/5)

=> 45 x 5 / 9

=> 5 x 5

=> 25 hours

Answer Link

Otras preguntas

8×3=(4×3)+(4×3)=Help me please and thank you!!
which of the following illustration the product rule for logarithms equations?
Laura has 9 apples jon has 6 apples how many apples do they have together
Arah wants to give the pizza delivery boy a 20 percent tip. If the pizza bill is $48.25, how much should she tip?
can someone help me plzzz... essay about global warming..and thank u guys
How did recordkeeping differ in ancient Egypt and the Incan Empire? A The Egyptians used cuneiform, but the Incans used hieroglyphics. B The Egyptians used hi
Impure and pure substance
Liam has 3 boxes of baseball cards with 50 cards in each box. He also has 5 boxes with 40 basketball cards in each box. If claim goes to the store and buys 50 m
A hospital cafeteria has 20 20 tables. 65% 65 % of the tables have 6 6 chairs at each table. The remaining 35% 35 % of the tables have 4 4 chairs at each t
3 examples Allied powers